On the third time up, dangerous ladders, and the arch that was always the hardest part.
I was able to spend some time over the last two days working on the arch of the wood kiln I am building. Itโs the third time putting it up, as the first two times were practice to be sure I had the correct bricks in the correct places so the arch would tighten when the center key brick was placed in and tapped tight with a rubber mallet. The kiln books I read paid off, as they gave me tips and information on how to build the arch of the kiln correctly.
Working near the top of the arch can be dangerous, and I had to climb up and down the ladder as I handled the bricks to be placed in. I also needed to make sure they were level and place wood shims where needed. This whole project has taken me about three years, as I also had to dismantle the kiln at another site. With each row of bricks I am able to lay in, I feel happy about getting closer to finishing the arch, as it was the most difficult part. I hope to have the arch finished in a day or two, then need to start the cover for the firebox and put up the chimney.
The firebox should go quite fast, as I have much of the brick to put it on. It is made of handmade tatami brick, and once on, I will need to fire it out to harden up the fire clay mortar. The tatami brick roof on the firebox will have six vent holes with plugs that I can open and close if needed based on draft intake when firing wood and also to let out exhaust when using the firebox as a kiln. The kiln will be one of the few to have a firebox that also fires as a kiln.
The chimney will just be a straight build and should go quite quickly. It was twenty feet in height when I took it down. I just need to be sure the draft ports and the air intake for secondary air are built in. The secondary air is sucked in through the chimney so that it does not take as much heat from the ware chamber. There will also be two side dampers so that the gap between the ware chamber and chimney can be managed. However, for now the main priority is getting that arch up.

If I were living yesterday a second time: I would have started earlier in the morning before the heat came in.
Things I am grateful for: Three years of slow progress that is finally showing up as a kiln.
If I get to live to be 86, I might only have: 12,618 days left.
Enjoyed this post? Get The Pottery Dailies delivered to your inbox every day.ย Subscribe on Substack.
Connect with Creek Road Pottery LLC:
Websiteย |ย Shopย |ย Collectors Clubย |ย The Pin Tool Podcastย |ย Instagramย |ย Bluesky